SR141/I-95 Ramp interchange Project

The Delaware Department of Transportation's (DelDOT) contractor, Mumford & Miller, Inc., continues the demolition of the SR141 northbound bridge. The contractor continues to perform the following work:  

  • Clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening.
  • Driving piles, pouring footers and have started the construction of the new bridge on SR141 southbound.

LANE CLOSURES:

Motorists should expect traffic on SR141 southbound to be reduced to one lane in the construction area during the hours of 9AM to 3PM, Monday thru Friday.

Motorists should expect traffic on SR141 northbound to be reduced to one lane in the construction area during the hours of 9AM to 3PM AND 6PM to 5AM, Monday thru Friday.

There will be mulitiple lane closures on NB I-95 during the evening hours from 6PM to 5AM, Monday thru Wednesday.

Ramp Exit 5B ( NB I-295 to NB SR141 ) remains closed until late June 2017. Northbound SR141 should use Exit 5.

 