View Article
DelDOT Advisory - REVISED DATES: SR 141/I-95 Ramp Interchange Project Will Require Nighttime Lane Shifts on I-95 NB and I-295 NB
By JSalmon on 07/07/2017: 0 Comments  

REVISED DATES: SR 141/I-95 Ramp Interchange Project Will Require Nighttime Lane Shifts on I-95 NB and I-295 NB

The Delaware Department of Transportation's (DelDOT) contractor, Mumford and Miller Inc. from 8 p.m. until 5 a.m. on the following nights: Monday, July 10 through Wednesday, July 12; and Tuesday, July 18, will be shifting traffic on I-95 northbound to I-295 northbound between Exit 5 and past SR 141 northbound interchange.
Beginning at 8 p.m. until 5 a.m. on Thursday, July 13; Friday, July 14; Monday, July 17 through Thursday, July 20; I-295 northbound will be closing/shifting lanes to I-95 northbound. The contractor will be removing the old bridge.

Nighttime Temporary Lane Closures/Lane Shifts with Exit Closure

Monday, July 10 through Wednesday, July 12; and Tuesday, July 18 (Nighttime Lane Shift)

I-95 northbound motorists will use the right lane signed for I-295 northbound and stay on the right lane of I-95 and then use the temporary crossover just past the work zone to go back onto I-295.

Thursday, July 13; Friday, July 14; and Tuesday, July 18 through Thursday, July 20 (Nighttime Lane Shift)

I-295 northbound motorists will use the right lanes signed for I-95 northbound and stay on the left lane of I-295 and then use the temporary crossover just past the work zone and go back onto I-95 northbound.

Thursday, July 20 (Nighttime Exit/Ramp Closure)

Exit 2/SR 141 southbound to I-295 northbound will be closed. Motorists traveling on SR 141 southbound will follow detour signage to US 13 north to I-295 to get to I-95 northbound